Residential demolition Central Coast: approvals, asbestos and timing
By Artigellence ·
A house can be demolished as complying development under the state Demolition Code, according to the NSW Planning Portal, but some properties need a full development application instead. The council's page says assessments have averaged 88 days over the last 12 months, so the approval path decides your timeline. Whichever path applies, the asbestos check has to happen before any demolition work starts.
Call (02) 4313 3101
Which approval path a house demolition takes
The NSW Planning Portal says the Demolition Code lets a dwelling be demolished as complying development, and the same code covers garages and swimming pools. For an ordinary house, that is the pathway to ask a certifier about first.
The alternative is a development application lodged with council, and that is where timing can blow out. Central Coast Council says it is "currently experiencing longer processing times for development applications." The council's page says assessments have averaged 88 days over the last 12 months. That is an average, so individual applications can come in faster or slower, but it is a sensible figure to plan around if your property cannot use the complying route.
Heritage listings and unstable ground
Heritage is the most common reason a simple knock-down turns into a longer process. Central Coast Council's heritage chapter says an application to demolish all or part of a heritage item, or a structure in a heritage conservation area, will only be considered with supporting documents. These are a development application for an appropriate replacement building, a heritage impact statement that covers options for adaptive reuse, and a demolition report.
The council's heritage advice page adds that some work on heritage items and on properties in heritage conservation areas needs a development application, and it recommends contacting council before starting.
Ground conditions can matter too, particularly if you are planning to rebuild. The council's geotechnical chapter says that where a lot is assessed at a hazard category of 2 or above, the development application must come with a geotechnical report covering stability on the site and on neighbouring lots.
Asbestos comes before the excavator
SafeWork NSW sets out the order of events plainly. The asbestos register is checked before demolition begins, a competent person inspects the structure if there is no register, and all asbestos is removed before demolition work starts.
This is not a remote risk. The NSW asbestos website estimates that around one in three houses in NSW built or renovated between 1945 and 1990 contain asbestos. If your home falls in that window, expect the inspection to turn something up.
On who does the removal, the Planning Portal's knockdown-rebuild guidance says to use a specialist asbestos removal contractor, notes that some demolition companies carry out asbestos removal as well, and warns that some types of asbestos removal need planning consent.
Loose-fill asbestos insulation is a special case. The NSW Government says the only way to remove it completely is to demolish the building and remediate the land.
Checking the contractor and planning the rebuild paperwork
Hiring matters beyond quality of work. SafeWork NSW says its inspectors can issue on the spot fines to an individual or business that appoints a demolition contractor who does not hold the authorisation the work requires. Ask for proof of that authorisation before you sign anything.
If a new house is going up afterwards, the paperwork continues. Central Coast Council's waste chapter requires a Resource and Waste Management Plan to be submitted and approved as part of the application for each new development on the Central Coast. Council also says a road opening permit is needed for road opening works, which include sewer connections, stormwater connections and water tapping for the new house.
Sorting these items early, before a demolition date is locked in, is what keeps a knock-down from stalling halfway.
Artigellence is the marketing business that operates this site and writes its articles. It does not carry out the work described.